Effektiviseradtidsplanering-Platsbaserad tidplanering och traditionell tidplanering
Örebro University, School of Science and Technology.
2014 (Swedish)Independent thesis Basic level (degree of Bachelor), 10 credits / 15 HE creditsStudent thesisAlternative title
Locationbased Scheduling and Traditional Scheduling (English)
Abstract [sv]

Den svenska byggbranschen kan utvecklas inom en rad olika områden för att effektivisera

produktionstiden. Målet för produktionstidplanering är att skapa förutsättningar för ett bra

produktionsresultat vid varje enskild byggnation.

Gantt-schema används som planeringsverktyg sedan en lång tid tillbaka och ger en

överskådlig bild av vad som ska göras och när det ska göras. Det har både sina för- och

nackdelar. Dagens planeringsteknik erbjuder stora möjligheter till förbättring av helhetsbilden

av byggprojekt. Detta ger möjligheter att göra en tidplan utan glapp, luft och kollisioner. I

synnerhet kan tid sparas vilket ger en positiv inverkan på ekonomin och vinsten.

Vico Schedule Planner (V-SP) har studerats för att få en bild över hur programmet lämpar sig

för planeringsändamål. En tidplan för ett verkligt byggprojekt har genomförts i V-SP med

hjälp av information från projektets kalkyl och 3D-modell. Tidplanen har planerats i Flowline

som bygger på platsbaserad tidsplanering, men samtidigt visas planeringen upp i ett Ganttschema.

Att göra en tidplan i V-SP minskar risker, glapp, luft och kollisioner. En bättre

helhetsbild fås vilket gör att dessa problem blir uppenbara vid planeringen. Projektet kan få en

lönsammare och effektivare byggproduktionstid. En jämn resursplanering kan fås och detta

värdesätts högt.

Nyckelord

Abstract [en]

The Swedish construction industry can develop a variety of things to efficiency production

time. The goal of production scheduling is to create conditions for good production results at

each building site.

Gantt scheduling has been used as a planning tool for a long time. The plan gives a clear

picture of what will be done and when it should be done. It has both its advantages and

disadvantages. Today’s technologies offer great opportunities for improvement of the overall

picture of the building project. This provides opportunities to make a schedule without

glitches, air and collisions. In particular, time can be saved which has a positive impact on the

economy and profits.

Vico Schedule Planner (V-SP) has been studied to obtain a picture of if the program is

suitable for planning. A timetable for a real project has been implemented in V-SP by aid of

information from the project calculations and 3D model. The schedule has been planned in

Flowline based on location based scheduling, but the Gantt schedule was also obtained.

Setting a timetable in V-SP reduces risks, glitches, air and collisions. A more complete picture

is obtained where these problems become apparent. The project can receive a more profitable

and efficient building delivery time. A steady resource use level can be obtained and this is

highly appreciated.

Place, publisher, year, edition, pages
2014. , p. 44
Keywords [sv]
Gantt schema, Flowline, Planering, Tidplan, Vico Software, Vico Schedule Planner, 4Dmodell
National Category
Civil Engineering
Identifiers
URN: urn:nbn:se:oru:diva-38254OAI: oai:DiVA.org:oru-38254DiVA, id: diva2:759502
Subject / course
Construction Engineering
Supervisors
Examiners
Available from: 2014-11-06 Created: 2014-10-30 Last updated: 2017-10-17Bibliographically approved

Open Access in DiVA

No full text in DiVA

By organisation
School of Science and Technology
Civil Engineering

Search outside of DiVA

GoogleGoogle Scholar

urn-nbn

Altmetric score

urn-nbn
Total: 196 hits
CiteExportLink to record
Permanent link

Direct link
Cite
Citation style
  • apa
  • ieee
  • modern-language-association-8th-edition
  • vancouver
  • Other style
More styles
Language
  • de-DE
  • en-GB
  • en-US
  • fi-FI
  • nn-NO
  • nn-NB
  • sv-SE
  • Other locale
More languages
Output format
  • html
  • text
  • asciidoc
  • rtf